2022 Construction Projects
Traffic/Intersection Improvements
Pearl Street/Ivory Street/John Mahar Highway Intersection - Intersection Redesign
King Hill Road/Pond Street/Granite Street Intersection - Intersection Study
Roadway Infrastructure Program
Roadway | Section | Project Scope |
Argyle Road Adams Street Bradford Road Cain Avenue Commercial Street Donata Road Elm Street Federal Drive Fern Road Glenrose Avenue Hawthorn Road Hooker Street Marianne Avenue Middle Street O'Toole Terrace Railroad Street Richardi Lane River Street Warren Avenue Washington Street | Entire Elm to Arnold Cain to Wildwood Entire Elm to Front Entire Route 3 Overpass to Old Elm Entire Entire Entire Entire Entire Entire Elm to Myrtle Entire Entire Entire Washington to Railroad Entire Pearl Street to Taylor Street | Roadway and Sidewalk Reconstruction Roadway Resurfacing Roadway and Sidewalk Reconstruction Roadway and Sidewalk Reconstruction Roadway and Sidewalk Reconstruction Roadway Resurfacing Roadway and Sidewalk Reconstruction Roadway Resurfacing Roadway and Sidewalk Reconstruction Roadway and Sidewalk Reconstruction Roadway and Sidewalk Reconstruction Roadway and Sidewalk Reconstruction Roadway Resurfacing Roadway and Sidewalk Reconstruction Roadway and Sidewalk Reconstruction Roadway and Sidewalk Reconstruction Roadway Resurfacing Roadway and Sidewalk Reconstruction Roadway Resurfacing Roadway Resurfacing |
Water Projects
Replace the watermains, reclaim the roadways and place binder on the following streets.
- Quincy Avenue (Allen St to Quincy Line)
Sewer Projects
Sewer Inflow and Infiltration Reduction Project, Years 8 and 9
Braintree performs sewer maintenance and repairs in a systematic two-year approach, the first year is an "investigation year" and includes cleaning and televising the inside of municipal sewer pipes which provides necessary system maintenance and identifies any issues that require further attention which can be addressed in the following "Rehabilitation Year". The rehabilitation work includes the lining of sewer pipes and manholes and sealing of joints and other defects with the goal of reducing the amount of groundwater infiltrating into the municipal sewer system. The majority of this work is trenchless and non-invasive, and often, residents will only see contractor vehicles parked in the middle of the street with access to the sewer system through manholes. This is a fairly expansive program that rehabilitates tens of thousands of feet of pipe in various sections of town. List of roads scheduled to be investigated and rehabilitated this year can be found at the links below.
Street Listing - Sewer Rehabilitation Year 8
Street Listing - Sewer Investigation Year 9
Howard Street Pump Station
The upgrade and modernization of an aging sewer pump station, including structural repairs to the rood of the structure and replacement of pumps, channel grinders and equipment. The project also includes the installation of a flow meter. Work is expected to be completed this Spring.
Miscellaneous Projects
Elder Affairs Parking Area
Resurface the existing parking area and expand the parking lot. This project is finished.